承包商在FIDIC合同条件下的变更工作思路与实施要点 被引量:3

Variation work thoughts and implementation points of contractors under FIDIC contract conditions
下载PDF
导出
摘要 变更管理低效是国内承包商在国际工程项目实施过程中的主要短板之一,为促进变更管理水平和变更工作质量提升,基于FIDIC合同条件中变更分类、责任承担/利益分享机制,分别从主动变更和被动变更两方面分析承包商变更应用要点。并以东欧黑山南北高速公路项目线路改移变更为案例,分析将工程量变化引起的变更成功转化为价值工程运用的方法,进一步总结提出承包商在FIDIC合同条件下的变更工作思路建议和实施要点。 Poor variation management is one of the main shortcomings of domestic contractors in implementing the international projects, in order to promote the variation management level and improve the variation work quality, based on the summary of variation classification, liability/interest share in FIDIC contract conditions, the variation application points of contractor are analyzed from active variation and passive variation respectively. Taking the route variation of the North-South Expressway Project in Montenegro, eastern Europe as an example, through analyzing the method of transforming the variation caused by engineering quantity into the application of value engineering successfully, the suggestions of variation work thoughts and implementation points of contractors under FIDIC contract conditions were further summarized and put forward.
作者 罗良乾 张捷 LUO Liang-qian;ZHANG Jie(CCCC Tianhe Mechanical Equipment Manufacturing Co., Ltd., Nanjing, Jiangsu 211899, China)
出处 《中国港湾建设》 2019年第4期78-82,共5页 China Harbour Engineering
关键词 FIDIC 工程变更 主动变更 价值工程 FIDIC project variation active variation value engineering
  • 相关文献

参考文献6

二级参考文献27

共引文献26

同被引文献15

引证文献3

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部