摘要 为解决电厂建成投产后重件码头的闲置问题,根据生产营运需要将其改造为专业化散货装船泊位。通过装船机和水平输送设备的合理选型,解决了码头长度不足和水平输送路由问题,同时很好地解决了散料输送过程中的环境污染问题。 The heavy cargo wharf be transformed into a specialized bulk cargo loading berth according to the demands of production and operation after the power plant is completed and put into operation so as to avoid the idle of the heavy cargo wharf. Through reasonable type selection of ship loader and horizontal conveying equipment, problems of insufficient wharf length and horizontal conveying route are solved, and the environmental pollution during bulk conveying can be well settled.
作者 周俊 何继红 Zhou Jun;He Jihong
出处 《起重运输机械》 2019年第6期83-85,共3页 Hoisting and Conveying Machinery
关键词 重件码头 直线摆动式装船机 管状带式输送机 heavy cargo wharf linear swing loader: pipe conveyor