提高堤防格宾石笼施工质量一次验收合格率 被引量:3

Improvement of dike gabion stone cage construction quality acceptance rate
下载PDF
导出
摘要 本文围绕提高堤防格宾石笼施工质量这一课题,进行现状调查、数据分析,进而确定问题症结。从"5M1E"(人、机、料、法、环、测)因素出发对症结进行了分析,确定"没有挂线施工"为要因,制定相应对策并实施。最后进行成果检验,合格率达到了预定目标,缩短了工期,节约了施工成本。 Status survey and data analysis are conducted in the paper aiming at the subject of improving the quality of embankment gabion stone cage construction, thereby determining the crux of the problem. The crux is analyzed from the factor of “5M1E”(human, machine, material, method, environment and measurement), thereby determining the cause of construction without hanging line’. Corresponding countermeasures are formulated and implemented. Finally, the results are tested, and the qualified rate reaches the predetermined target, thereby shortening the construction period, and then saving the construction cost.
作者 朱积有 林伟东 汪璐 ZHU Jiyou;LIN Weidong;WANG Lu(Shaanxi Sanhe Construction Engineering Co. , Ltd. , Xi ’an 710032, China;Shaanxi Water Conservancy Construction Administration Bureau, Xi ’an, 710032, China)
出处 《水资源开发与管理》 2019年第3期75-78,共4页 Water Resources Development and Management
关键词 堤防 格宾石笼 挂线 合格率 embankment gabion stone cage line hanging acceptance rate
  • 相关文献

同被引文献14

引证文献3

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部