摘要
介绍了某超高压变电站集中检修现场的安全风险管控,主要对变电站集中检修现场存在的安全风险进行了分析,并以500 kV众兴变集中检修作业为例,从作业准备、作业实施、作业终结验收3个阶段入手,针对性地提出了风险管控措施,具有一定的借鉴意义。
This paper introduces the safety risk control of a centralized maintenance site in an ultra-high voltage substation,mainly analyzes the safety risks existing in the centralized maintenance site.By taking the centralized maintenance operation of 500 kV Zhongxing substation as an example,it puts forward the risk control measures from three stages such as operation preparation,operation implementation and final acceptance,which can be referred by the other ultra-high voltage substations.
作者
郑晓琼
江海升
王鹏辉
陶梦江
徐文婷
ZHENG Xiaoqiong;JIANG Haisheng;WANG Penghui;TAO Mengjiang;XU Wenting(State Grid Anhui Maintenance Co.,Ltd.,Hefei 230061,Anhui Province,China;Anhui Mingsheng Power Development Investment Group Co.,Ltd.,Hefei 230061,Anhui Province,China)
出处
《电力安全技术》
2019年第2期4-7,共4页
Electric Safety Technology
关键词
超高压变电站
集中检修
安全风险
管控
ultra-high voltage substation
centralized maintenance
safety risk
management control