天然气蒸汽转化炉运行中存在的问题及解决措施

Problems Existing in Operation of Natural Gas Steam Reformer and Its Solutions
下载PDF
导出
摘要 通过对天然气蒸汽转化顶部烧嘴转化炉在运行中出现的转化管在距顶部2~4米范围蠕变破裂、转化管弯曲变形、烧嘴火焰刚性差、火焰局部添管等异常现象和长周期运行时间短的问题进行技术分析,在此基础上从燃烧系统、转化炉炉管材质和维护保养、炉管恒力弹簧支吊架的载荷与热位移方面提出了切实有效的解决措施,并予以实施,取得了良好的效果,延长了装置长周期运行时间。 Based on technical analysis of abnormal phenomena such as creep rupture of the reforming pipe in the range of 2~4 m from the top, bending deformation, poor flame rigidity of burner, partial pipe addition of flame and short running time of reformer tube in the operation of top burner reformer for natural gas steam reforming, the combustion process was discussed. The system, the material and maintenance of converter tube, and the load and thermal displacement of the constant force spring support hanger of furnace tube were put forward and implemented, which achieved good results and prolonged the long-term running time of the device.
作者 唐勇 TANG Yong(Chongqing Changfeng Chemical Co., Ltd., Chongqing 401120, China)
出处 《广州化工》 CAS 2019年第7期127-129,共3页 GuangZhou Chemical Industry
关键词 转化炉运行 存在问题 措施 效果 reformer operation existing problems measures effect
  • 相关文献

参考文献3

二级参考文献16

  • 1Paredes M, Sartor M, Masclet C. Obtain an optimal compressing spring design directly from a user specification [J]. Engineering Manufacture, 2002,216 : 419-428.
  • 2Paredes M,Sartor M, Masclet C. Finding the optimal stock spring from optimal spring design characteristics [J]. Mechanical Engineering, 2002 : 465-472.
  • 3西安交通大学材料力学教研室.材料力学[M].西安:西安交通大学出版社,1990.
  • 4Schillmoller C M. Solving High - Temperature Problems in Oil Refineries and Petrochemical Plants, Materials Engineering, 1984,63 (12)
  • 5Hahmann F W. Improve Steam Reformer Performance,Petorchemical Developments, 1983,62 (1)
  • 6Agarwal D C. Recent Results on Metal Dusting of Nical Base Alloys and Some Applications, Corrosion, 2001, P01382
  • 7.API Publication 535.一般炼油装置火焰加热炉用燃烧器[Z].,1995..
  • 8GB6393-86.金属高温拉伸试验法.[S].,..
  • 9王富岗 王焕廷.石油化工高温装置材料及其损伤[M].大连理工大学出版社,1982..
  • 10彭进.管道设计中支吊架的正确设置[J].炼油设计,1999,29(5):54-58. 被引量:14

共引文献12

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部