摘要
以某工程屋面型钢井字梁安装为载体,确定吊装设备和安装顺序,有效地保证了施工过程中型钢井字梁的受力稳定性和施工后的整体质量,以期能为同类型结构的施工提供宝贵经验和可靠依据。
Taking the installation of a section-steel-cross-beam stage roof as an example,this paper discusses the determination and installation sequence of hoisting equipment,in order to effectively guarantee the stress stability of the section steel cross beam in the construction and the overall quality after construction,hoping to provide valuable experience and reliable basis for the construction of similar structures.
作者
刘保忠
LIU Bao-zhong(Shanxi Polytechnic College,Taiyuan,Shanxi,030006,China)
出处
《建材技术与应用》
2019年第2期24-26,共3页
Research and Application of Building Materials
关键词
大重量
屋面
型钢井字梁
安装施工
heavy weight
roof
section steel cross beam
installation and construction