对清河采油厂稠油区块集输管网改造工程的投资完成、实际经济效益与可行性研究报告预期指标进行了对比分析,投资控制在了可行性研究报告指标内,经济效益达到预期指标要求,为今后类似稠油区块集输管网改造项目经济预评估和后评价可提供一定的借鉴作用。
This paper analyzes by contrast completed investment to gathering pipeline network modification engineering of heavy oil blocks in Qinghe Oil Production Plant,actual economic benefit and predicted indexes in feasibility research report.The result shows that the investment is controlled within the feasibility research report index and economic benefit reaches expected index demand,providing a certain reference for economic pre-assessment and post-assessment on future gathering pipeline network modification in similar heavy oil blocks.