摘要
以子47-1井和子6-4井注水泥浆堵漏发生“插旗杆”事故为例,介绍了其处理过程。通过分析事故原因,制定出解决措施,对今后处理井漏时避免发生“插旗杆”事故有一定的借鉴作用和参考价值。
Taking the“flag pole”accident of cement slurry plugging in well Zi 47 1 and well Zi 6 4 as an example, the treatment process is introduced in this paper.Through the analysis of the cause of the accident and the formulation of the solving measures, it has certain reference and reference value to avoid the occurrence of the“flag pole”accident when dealing with the well leakage in the future.
作者
庞方言
毛亚军
孙渊珍
李鹏
景雪
Pang Fangyan;Mao Yajun;Sun Yuanzhen;Li Peng;Jingxue(Shannxi Yanchang Petroleum Group Oil and Gas Exploration Company Yanchang Gas Field No.1 Plant,Shaanxi Yanan 716000)
出处
《云南化工》
CAS
2019年第3期175-176,179,共3页
Yunnan Chemical Technology
关键词
井漏水泥浆
插旗杆
措施
well leakage cement slurry
flagpole insertion
measures