汉钢2280m^3高炉超计划检修48h炉况恢复生产实践 被引量:2

Production practice of restoring furnace conditions of hansteel 2280m^3 blast furnace after over-scheduled maintenance for 48h
下载PDF
导出
摘要 汉钢2 280 m^3高炉检修中发现炉顶布料溜槽倾动故障,高炉被迫延迟送风48 h进行更换,通过优化复风方案,合理控制各项操作参数,复风60 h后,主要经济技术指标已恢复至正常冶炼水平. In the maintenance of Hansteel's 2 280 m^3 blast furnace, the distributing chute titling fault was found on the top of furnace roof. Thus, the blast furnace was forced to delay the air supply for 48 hours. Then the scheme of recovering wind was optimized, and operating parameters were appropriately controlled. Therefore, the major economic and technical indicators were restored to normal smelting level after the recovery of wind for 60 hours.
作者 冯磊 侯向平 FENG Lei;HOU Xiangping(Hanzhong Iron & Steel Co.,Ltd. of Shanxi Iron & Steel Group, Mianxian 724200,China)
出处 《江西冶金》 2019年第2期46-50,共5页 Jiangxi Metallurgy
关键词 高炉 操作参数 炉况恢复 经济技术指标 冶炼水平 blast furnace operating parameters recovery of furnace condition economic and technical Indicators smelting level
  • 相关文献

参考文献4

二级参考文献6

共引文献18

同被引文献6

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部