摘要
杜儿坪煤矿在南九盘区72909工作面推广应用了切顶卸压护巷技术,通过在72909皮带巷不采帮侧开展切顶卸压、预裂切缝、预裂爆破施工,对邻近72909瓦斯预抽巷围岩进行了保护,加强了该巷道切顶护巷支护工艺,延长了巷道服务年限,减小了因采动压力影响而造成的巷道变形量增大,降低了巷道维护治理费用。
Du’erping Mine applied "roof cutting and pressure relief roadway protection technology" in 72909 working face of Nanjiupan District. Through roof cutting and pressure relief, pre-splitting and pre-splitting blasting was constructed on the side of non-mining side of 72909 belt roadway, the surrounding rock of adjacent 72909 gas pre-drainage roadway was protected, the roof cutting and roadway protection technology was effectively strengthened, the service life of roadway was prolonged, and the influence of mining pressure caused by roadway deformation was reduced, with the lower cost of roadway maintenance and treatment.
作者
李卯玄
张卓
Li Maoxuan;Zhang Zhuo(Du’erping Mine,Xishan Coal and Electricity Group, Taiyuan 030022, China)
出处
《煤炭与化工》
CAS
2019年第3期18-22,共5页
Coal and Chemical Industry
关键词
切顶卸压
护巷
预裂切缝
围岩应力
cutting top pressure relief
roadway protection
pre-split slit
surrounding rock stress