新疆某水利枢纽工程泄洪闸水工模型试验研究 被引量:5

Experimental Study on the Hydraulic Model of the Flood Gate of Some Hydro-project in Xinjiang
下载PDF
导出
摘要 新疆某拦河引水枢纽工程等别为Ⅰ等大(1)型,泄洪闸规模为6孔闸,每孔净宽11m,通过水工模型试验对泄洪闸泄流能力、水流流态等水力特性的综合研究,提出可通过优化泄洪闸体型及加深加长下游消力池来增大消能率。结果可为工程设计提供参考。 A certain river diversion pivot project in Xinjiang is the I(1)type,the size of the flood discharge gate is 6-hole gate,and the net width per hole is 11m.The hydraulic characteristics of the flood discharge gate are combined by the hydraulic model test.Research suggests that the energy dissipation rate can be increased by optimizing the floodgate type and deepening the downstream stilling pool.The results can provide a reference for engineering design.
作者 周旭锐 Zhou Xurui(Xinjiang Water Resources and Hydropower Survey and Design Institute,Urumqi 830000,Xinjiang)
出处 《陕西水利》 2019年第5期126-128,132,共4页 Shaanxi Water Resources
关键词 泄洪闸 模型试验 设计优化 Flood gate the model test and design optimization
  • 相关文献

同被引文献35

二级引证文献23

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部