摘要 为防止东偏泓闸上游船只对水闸的运行管理带来安全隐患,需要在上游设置拦船设施,起到安全警示作用。基于力学原理及规范公式,采用受力分析法,对新建拦船设施的安全稳定、地锚阻水以及由此带来的冲刷等问题进行计算分析。结果表明:新建拦船设施整体稳定性好,混凝土地锚的设置对东偏泓闸行洪基本没有影响。该工程所采用的设计方案与计算方法可供类似项目参考与借鉴。 In order to prevent the safety of the sluice operation and management of the upstream vessels of the east-biased gate,it is necessary to set up a ship-blocking facility upstream to play a safety warning role.Based on the mechanics principle and the normative formula,the force analysis method is used to calculate and analyze the safety and stability of the new ship-building facilities,the ground anchor water blocking and the resulting erosion.The results show that the overall stability of the new ship-blocking facilities is good,and the setting of the concrete ground anchors has no effect on the flooding of the east-south gate.The design scheme and calculation method adopted by the project can be used for reference and reference of similar projects.
作者 沈芝莹 陈猛 陈洁茹 王亚妮 Shen Zhiying;Chen Meng;Chen Jieru;Wang Yani(Huai'an Water Resources Survey and Design Institute Co.,Ltd. Huai'an 223005,Jiangsu)
出处 《陕西水利》 2019年第5期133-134,137,共3页 Shaanxi Water Resources
关键词 拦船设施 受力分析 安全稳定 影响分析 Ship blocking facility force analysis safety and stability and impact analysis
  • 相关文献

参考文献1

二级参考文献4

共引文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部