期刊文献+

论盾构施工穿越既有地铁运营线路的控制措施 被引量:3

On the Control Measures of Shield Construction Crossing Existing Subway Operation Lines
下载PDF
导出
摘要 中-松盾构区间上跨既有崇岐运营线路区间施工难点是两线间距小、始发段长度较短,施工中通过将盾构机选型、掘进参数控制、刀盘前方渣土改良以及既有线和新建线路的监控量测等措施相结合,达到盾构施工通过既有线的目的,为其他类似工程施工提供借鉴意义。 The difficulties in the construction of the Zhongsong shield section across the existing Chongqi operation line section are small distance between the two lines and short length of the starting section. The shield construction can pass through the existing line by combining shield machine selection, tunneling parameter control, muck improvement in front of cutter head, monitoring and measurement of existing line and new line.
作者 雷杨 LEI Yang(China Railway 18th Bureau Group 5^th Engineering Co.,Ltd. Tianjin 300000 China)
出处 《石家庄铁路职业技术学院学报》 2019年第2期76-80,共5页 Journal of Shijiazhuang Institute of Railway Technology
关键词 盾构 上跨既有线 措施 shield upper span existing line measures
  • 相关文献

同被引文献20

引证文献3

二级引证文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部