摘要
汕头某大桥工程位于东海岸新城,横跨出海口,为城市快速路,西岸引桥为双向八车道、单幅桥面宽21.85m的单箱三室连续梁,采用碗扣式满堂支架现浇施工技术,施工过程中做好满堂支架搭设施工方案、满堂支架预压及监测措施,实施现浇箱梁模板安装、支座安装、混凝土浇筑和养护、预应力管道安装、预应力筋张拉和压浆等施工技术,取得预期施工技术效果。
A bridge project in Shantou is located in the East Coast New City,across the sea,as the urban expressway,the west bank approach span of eight lanes,single deck width 21.85 m single box three-chamber continuous beam,the button bowl full framing cast-in-situ construction technology,construction process and support build-up construction scheme,full framing preloading and monitoring measures,implementation of cast-in-situ box girder template installation,bearing installation,concrete pouring and curing and prestressed pipe installation,tensioned prestressed reinforcement and grouting construction technology,to obtain the expected effect of construction technology.
作者
何沁洲
He Qinzhou(Guangdong Baohui Construction Engineering Co.,Ltd. Shantou 515041,China)
出处
《广东土木与建筑》
2019年第6期43-45,共3页
Guangdong Architecture Civil Engineering
关键词
大型桥梁
单箱三室混凝土箱梁
现浇施工技术
large bridge
single box three chambers concrete box girder
cast-in-place construction technology