摘要
在LNG接收站建设中,储罐的施工是一项技术难点。本课题选取16万立方米大型LNG储罐安装施工这个阶段,主要针对LNG储罐的安装工程施工工序及方法进行探讨,论述LNG储罐建设过程中罐内外设备、管材安装焊接施工的实际应用。
In the LNG receiving station construction,the storage tank construction is a technical difficulty. This project selects the installation and construction stage of 160,000 cubic meters of large LNG storage tanks,mainly discusses the installation process and method of LNG storage tanks,and discusses the practical application of installation and welding of internal and external equipment and pipes in the construction process of LNG storage tanks.
作者
王刚
Wang Gang(Sinopec Tianjin LNG Co.,LTD.,Tianjin 300457)
出处
《石化技术》
CAS
2019年第5期9-9,23,共2页
Petrochemical Industry Technology
关键词
LNG储罐
安装施工
工序
方法
LNG storage tank
Installation and construction
Process
Methods