期刊文献+

复杂环境条件下的深大基坑三道内支撑体系设计与施工 被引量:3

Design and Construction of Three Internal Support Systems for Deep and Large Foundation Pit Under Complex Environment Condition
下载PDF
导出
摘要 结合苏州银座广场工程,对邻近运营地铁区间隧道的深基坑围护结构设计与施工工艺进行了介绍。并从栈桥施工、土方开挖运输、支撑破除等方面对深大基坑的施工重点、难点进行分析总结,以期为类似工程的施工提供借鉴。 Combi ned with the Ginza Plaza Project in Suzhou, the desig n and con structi on tech no logy of the deep foundation pit support structure adjacent to the subway tunnel in operation is introduced. The key and difficult points of large and deep foundation pit construction are analyzed and summarized from the aspects of trestle construction, earthwork excavation and transportation, support dismantlement, so as to provide reference for the construction of similar projects.
作者 虞坚 YU Jian(Zhongyifeng Construction Group Co., Ltd., Suzhou, Jiangsu 215131, China)
出处 《建筑施工》 2019年第5期747-750,共4页 Building Construction
关键词 深基坑 近地铁侧 支护 施工栈桥 deep foun dation pit side adjace nt to subway support con structio n trestle
  • 相关文献

参考文献8

二级参考文献13

共引文献43

同被引文献20

引证文献3

二级引证文献1