摘要
预应力钢筋混凝土连续梁悬浇施工时,悬臂两侧存在混凝土恒载、施工荷载和风荷载等不平衡荷载,为保证施工阶段悬臂主梁的抗倾覆稳定,要在墩身和主梁0号块上设置墩梁临时固结装置。结合某工程实例,进行墩梁临时固结装置的设计和计算,为类似工程项目提供参考。
In the suspended poured construction of prestressed reinforced concrete continuous beams, unbalanced loads such as dead load of concrete, construction load and wind load exist on both sides of the cantilever. In order to ensure the anti-overturning stability of the main beams of cantilever in the construction stage, temporary consolidation devices for pier beams should be installed on the pier body and block 0 of the main beam. Combining with a project case, the design and calculation of temporary consolidation devices for pier beams are carried out, so as to provide reference for similar engineering projects.
作者
韩少波
HAN Shao-bo(JSTI Group Co.,Ltd., Nanjing 210017, China)
出处
《北方交通》
2019年第6期33-36,共4页
Northern Communications
关键词
悬浇梁
墩梁临时固结
抗倾覆稳定
Suspended poured beam
Temporary consolidation of pier beam
Anti-overturning stability