摘要
通过对吴淞江工程(上海段)需建设跨河桥梁施工期间交通影响分析,结合吴淞江工程河道及桥梁建设计划、桥梁实施方案,提出吴淞江工程(上海段)跨河桥梁施工期间总体交通组织方案,为类似航道/河道整治涉及桥梁群改建的项目提供施工期间交通组织总体思路。
According to the traffic impact analysis during the construction of cross-river bridge in Wusong River Project (Shanghai Section), and combined with the river and bridge construction planning, and the bridge implementation scheme of Wusong River Project, this paper proposes the overall traffic organization scheme during the construction of cross-river bridge in Wusong River Project (Shanghai Section), which provides the general thought of traffic organization during the construction and reconstruction of the similar channels, rivers and bridges.
出处
《城市道桥与防洪》
2019年第6期52-55,M0008,共5页
Urban Roads Bridges & Flood Control
关键词
太湖流域整治吴淞江工程
桥梁群建设
施工期间交通组织
Wusong River Project of Taihu Lake Basin Regulation Project
construction of bridges
traffic organization during construction