摘要
某消防水池由于施工完成后,地下水位发生变化,导致水池被顶起,并发生倾斜,严重影响了该水池的正常使用。针对这一事故进行了详细地分析,认为该水池变形是由于局部抗浮设计不足所致。根据现场实际情况,提出合理的解决措施,使该水池能正常投入使用。
The underground water level of a fire water pond changed after the construction was completed,which seriously affected the normal use of this pond as it was jacked up and tilted.An in-depth investigation into the event suggested that the deformation of the pond was caused by irrational local anti-floating design.Based on the actual situation on site,reasonable countermeasures were proposed to ensure the pond be put into normal operation.
作者
吕红安
秦兆平
LV Hong-an;QIN Zhao-ping(Wuhuan Engineering Co.,Ltd,.Wuhan Hubei430223,China;Wuhan Engineering Consulting Agency,Wuhan Hubei430014,China)
出处
《化肥设计》
CAS
2019年第3期10-12,共3页
Chemical Fertilizer Design
关键词
水池
地下水
变形
抗浮
措施
water pond
underground water
deformation
anti-floating
countermeasures