摘要 以一座支架现浇斜靠式系杆拱桥为背景,基于正装迭代法对吊杆施工初张力进行了分析。分别采用目标值法、倒拆法、影响矩阵法确定迭代初始值,研究三种方法对吊杆施工初张力求解的精度和效率。结果表明:目标值法比倒拆法和影响矩阵法迭代收敛速度慢,但其获取初始值更为方便。当精度要求不高时,可采用倒拆法或影响矩阵法确定初始值,并进行一次正装迭代验算后确定吊杆施工初张力。 With a cast-in-situ leaned tied-arch bridge as the background, the preliminary tension of suspender construction is analyzed based on the forward iteration method. The initial iteration value is determined by respectively adopting the target value method, the backward analysis method and influence matrix method, and the accuracy and efficiency of preliminary tension solution are studied by these three methods. The results show that the target value method iterates and converges more slowly than the backward analysis method and the influence matrix method , but it is more convenient to achieve the initial value by adopting the target value method. When the accuracy requirement is not high, the backward analysis method or the influence matrix method can be used in determining the iterative initial value, and the preliminary tension of suspender construction can be determined after only one time check of forward iteration.
作者 李长坤 段庆普 魏玲利 Li Changkun;Duan Qingpu;Wei Lingli(Jinan Urban Construction Group Co. , Ltd. , Jiruin 250031;Jinan Peoples Vocational Secondary School, Jinan 250031)
出处 《工程建设》 2019年第5期42-46,共5页 Engineering Construction
关键词 斜靠式系杆拱桥 吊杆施工初张力 正装迭代法 目标值法 倒拆法 影响矩阵法 double X-shape arch bridge preliminary tension of suspender construction forward iteration method target value method backward analysis method influence matrix method
  • 相关文献

参考文献9

二级参考文献59

共引文献129

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部