摘要 国投哈密一矿通过对露天矿各煤层煤质的分析,并结合电厂对煤质的要求及单双机组供煤量的不同,根据露天采场的实际生产情况,提出了不同的开采方案和灌仓方案,确保供煤平稳高效的进行,更加高效的保障电煤煤质及煤量的要求,使储煤场发挥其应有的作用。 Through the analysis of coal quality of each coal seam in guotou Hami No.1 mine,combining with the requirements of the power plant on the coal quality and the amount of coal supplied by single and double units,and according to the actual production situation of the open-pit stope,Different mining schemes and silo filling schemes are put forward to ensure coal supply stable and efficient.the coal quality and amount of thermal coal are more efficiently guaranteed,so that the coal storage yard can play its role.
作者 宁大方 NING Dafang(China Coal Technology and Engineering Group Shenyang Design & Research Institute,Shenyang 110015,China)
出处 《露天采矿技术》 CAS 2019年第3期14-16,21,共4页 Opencast Mining Technology
关键词 储煤场 煤质 开采方案 灌仓方案 仓位预报 coal storage yard coal quality mining scheme silo filling
  • 相关文献

参考文献1

二级参考文献7

共引文献4

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部