摘要
为保证15号煤煤仓上部卸载硐室围岩的稳定,通过对卸载硐室的地质条件进行具体分析,并对围岩的变形量和塑性区分布进行数值模拟,决定采用"全断面长锚索+关键部位组合锚索+破碎带注浆"支护技术,结合卸载硐室的支护原理对卸载硐室断面1-1的加固方案进行具体设计,并对支护后的巷道进行矿压监测。结果表明,加固方案实施后,顶底板的最大移近量为94 mm,两帮最大移近量为55 mm,锚索受力均匀,保证了巷道围岩的稳定。
In order to ensure the stability of the surrounding rock of the unloading chamber in the upper part of No.15 coal bunker, the geological conditions of the unloading chamber were analyzed in detail, and the deformation and plastic zone distribution of the surrounding rock were numerically simulated. The long anchor cable + key part combination anchor cable+ fracture zone grouting" support technology, combined with the support principle of unloading chamber, the concrete design of the unloading chamber section 1-1 was designed, and the roadway after support was carried out. The results showed that after the reinforcement scheme,the maximum displacement of the top and bottom plates was 94 mm, the maximum displacement of the two sides was 55 mm, and the anchor cable was evenly stressed, which ensured the stability of the surrounding rock of the roadway.
作者
张永忠
Zhang Yongzhong(Zuoquan Xinshun Coal Industry Corporation Ltd., Shanxi Coal Import and Export Group Jmzhong 032699, China)
出处
《煤炭与化工》
CAS
2019年第5期45-48,共4页
Coal and Chemical Industry
关键词
卸载硐室
围岩控制
组合锚索
unloading chamber
surrounding rock control
combined anchor cable