超高层建筑核心筒施工主要设施配置及工序 被引量:3

Main facilities configuration and procedure for core tube construction of super-high-rise building
下载PDF
导出
摘要 针对中交汇通横琴广场3号主塔楼核心筒具有超高、层间距大、异形(椭圆形)、施工作业空间狭小、结构组合复杂等特点,阐述了核心筒剪力墙结构所包含钢结构安装、钢筋绑扎、模板支设等工序施工的主要工序控制,并对相关影响因素作了简要分析。通过采用液压爬升模板系统、合理布设塔吊及相关设施,规划各施工要素,使各工序施工衔接更加流畅、高效。 In view of the characteristics of core tube of No.3 main tower building of CCCC Hengqin Huitong Financial World, such as super elevation, high storey, special shape (ellipse shape), narrow construction space and complex structure combination, the main process control of steel structure installation, steel bar binding and formwork support in core tube shear wall structure is elaborated, and the related influencing factors are briefly analyzed. Through the use of hydraulic climbing formwork system, reasonable layout of tower crane and related facilities, planning of various construction elements, so that the construction process links up more smoothly and efficiently.
作者 李广慧 徐乐华 刘浩 柯思睿 LI Guang-hui;XU Le-hua;LIU Hao;KE Si-rui(No.4 Engineering Co., Ltd. of CCCC First Harbor Engineering Co., Ltd., Tianjin 300456, China)
出处 《中国港湾建设》 2019年第7期59-64,共6页 China Harbour Engineering
关键词 超高层 核心筒 爬模 工序 super-high-rise building core tube climbing formwork working procedure
  • 相关文献

参考文献8

二级参考文献14

共引文献69

同被引文献15

引证文献3

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部