摘要
在地铁施工过程中,基坑降水技术方法的选择与技术措施会直接影响工程质量。因此,各类深基坑降水及暗挖区间降水越来越受到重视。论文以某实际工程为例,分析了地铁降水施工的控制要点,并提出了降水监控技术管理措施,以供类似工程参考。
In the process of subway construction,the selection of dewatering technology and technical measures of the foundation pit will directly affect the project quality.Therefore,more and more attention has been paid to all kinds of deep foundation pit dewatering and excavation interval dewatering.Taking a practical project as an example,this paper analyzes the key points of the control of subway dewatering construction,and puts forward the dewatering monitoring technology and management measures for reference of similar projects.
作者
万正武
WAN Zheng-wu(The Third Engineering Co.Ltd.of the First Highway Engineering Bureau of CCCC,Beijing 101102,China)
出处
《工程建设与设计》
2019年第12期188-189,共2页
Construction & Design for Engineering
关键词
轨道交通
矿山法
降水施工
rail transit
mining method
dewatering construction