摘要
介绍了安徽省引江济淮工程杭埠河倒虹吸工程的基本情况,分析了其工程地质和水文地质。由于基坑开挖深度大、砂层承压水头高,施工期间面临的地下水控制问题难度较大,通过比较深井降水(采用承压—潜水完整井干扰井群公式计算)和地下连续墙围封两种方案,最终选定基坑围封方案。并论述了地下连续墙设计和施工中需要注意的问题。
An introduction was made on the general information of the Hangbu River inverted siphon work, one of the components of Yangtze River-to-Huaihe River Water Diversion Project. The engineering and hydrological geological conditions were analyzed. Deep excavation and sand layer withstanding high water pressure will lead to great difficulties for underground water control during the construction of foundation pit. Two alternatives of deep well dewatering and enclosed underground diaphragm wall were compared before the enclosed diaphragm wall scheme was selected, of which the deep well calculation was conducted with the formula of interference wells group for pressurediving complete wells. The author discussed the issues in need of special attention during design and construction of underground diaphragm wall.
作者
邹玉波
ZHOU Yu-bo(Anhui Survey and Design Institute of Water Conservancy and Hydropower, Hefei 230088, China)
出处
《广西水利水电》
2019年第3期19-23,共5页
Guangxi Water Resources & Hydropower Engineering
关键词
地下水控制
深井降水
干扰井群
地下连续墙
杭埠河倒虹吸
引江济淮工程
Underground water control
deep-well dewatering
interference well group
underground diaphragm wall
Hangbu River inverted siphon
Yangtze River-to-Huaihe River Water Diversion Project