摘要
通过分析公路和城市道路通行能力与车道数测算的影响因素、计算方法,总结了两种性质道路通行能力与车道数测算计算方法的不同以及工程中实际应用的一般做法,并以阜宁南站连接线工程为例,按照公路和城市道路性质计算车道数,给出合理建议,以指导道路横断面设计。
By analyzing the influencing factors and calculating methods of traffic capacity and lane numbev of highway and uvban voads, this paper summarizes the deferences of calculating methods and the general application in engineeang. Taking the connecting line project of Funing South Railway Station as an example, this paper calculates lane number accarding to the nature of highway and urban roads, and gives reesonable suggestions the guide the design of road cross section.
作者
李燕
Yan Li(China Railway Fifth Survey and Design Institute Group Co., Ltd. Beijing 102600, China)
出处
《青海交通科技》
2019年第1期30-33,48,共5页
Qinghai Transportation Science and Technology
关键词
高铁站连接线工程
通行能力车
道数测算
high - speed railway station connecting line
traffia capacity
lane numbeo calculation