大型炼油厂首次绿色停工检修难点分析及对策 被引量:4

Difficulties of the first green shutdown overhaul in large refinery and countermeasures
下载PDF
导出
摘要 针对国内某大型炼油厂首次停工检修技术难点,诸如:硫磺回收装置二氧化硫排放超标、新时期环保要求“气不上天,油不落地”、系统高温重污油管线密闭吹扫、硫化亚铁自燃风险及胺液系统回收储存难度大等,分别采取硫磺回收装置“热氮吹硫”、“密闭煮塔”、延迟焦化装置放空系统增设接收全厂吹扫污油线,钝化清洗及胺液提浓等措施,实现了首次绿色停工检修。 Aiming at the technical difficulties of the first shutdown overhaul in a large refinery in China, such as sulfur dioxide emission of sulfur recovery unit exceed the standard, environmental protection requirements "gas doesn’t go up, oil doesn’t fall to the ground" in the new period, closed purging of high temperature and heavy oil pipelines in the system, ferrous sulfide has self-ignition risk and amine fluid system is difficult to recover and storage, etc. The measures of "hot nitrogen sulfur blowing", "closed boiling tower" and "delayed coking unit emptying system add cleaning dirty oil line, passivation cleaning and concentration of amine solution, etc." are adopted respectively to realize the first green shutdown and maintenance.
作者 李建国 曹红斌 孙守华 Li Jianguo;Cao Hongbin;Sun Shouhua(SINOCHEM Quanzhou Petrochemical Co. , Ltd, Quanzhou, Fujian 362103)
出处 《炼油技术与工程》 CAS 2019年第6期36-39,45,共5页 Petroleum Refinery Engineering
关键词 绿色停工检修 热氮吹硫 钝化 清洗 胺液 green shutdown overhaul hot nitrogen blowing sulphur passivation cleaning amine
  • 相关文献

参考文献5

二级参考文献18

共引文献35

同被引文献20

引证文献4

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部