摘要
以成都地铁18号线盾构穿越人工湖为研究背景,对盾构机穿越人工湖的关键技术进行了研究。通过分析总结,表明技术可行,以期能为其他类似工程提供技术参考。
Based on the background of shield crossing artificial lake in Chengdu Metro Line 18,this paper studies the key technology of shield crossing artificial lake. Through analysis and summary,it shows that the technology is feasible,in order to provide technical reference for other similar projects.
作者
吴传意
杜书光
Wu Chuanyi;Du Shuguang(China Electricity Construction Group Railway Construction Co.,Ltd.,Beijing 100089,China)
出处
《山西建筑》
2019年第13期137-138,共2页
Shanxi Architecture
关键词
地铁
盾构
施工技术
subway
shield
construction technology