双塔串联脱硫系统除雾器堵塞原因分析与建议 被引量:4

Analysis and suggestion for blocking in mist eliminator of double tower series desulfurization system
下载PDF
导出
摘要 石灰石-石膏湿法双塔串联系统在我国超低排放改造进程中是较为常见的技术路线,该技术具有较强的技术特点,两座吸收塔均设置除雾器,需协调进行除雾器冲洗,运行控制不当时会频繁出现除雾器结垢堵塞以及塌陷问题。通过分析,对于双塔串联脱硫系统,水平衡不佳、浆液参数不合理、除雾器布置不合理、公用系统容量不足均会导致除雾器结垢堵塞。 The limestone-gypsum wet double tower series system is a common technical route in China's ultra-low emission reform process. This technology has obvious technical characteristics. Both towers are equipped with mist eliminator, which needs coordinated wash. Fouling and blocking problems occured frequently when operation control is not proper. Through the analysis, for the double tower series desulfurization system, the poor water balance, the unreasonable slurry parameters, the unreasonable placement, and insufficient capacity of the common system all will lead to blocking of the mist eliminator.
作者 张晓玲 党龙 陈军 王智 史成新 ZHANG Xiaoling;DANG Long;CHEN Jun
出处 《电力科技与环保》 2019年第4期41-43,共3页 Electric Power Technology and Environmental Protection
基金 中国华电集团公司科技项目“脱硫除雾器堵塞机理分析及预防措施研究”(SXNYKJ15-0101)
关键词 双塔串联 除雾器 堵塞 结垢 double tower series mist eliminator blocking scaling
  • 相关文献

参考文献16

二级参考文献118

共引文献169

同被引文献69

引证文献4

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部