摘要
在矿山的建设过程中,斜井是其非常重要的组成部分,由于地址情况、施工工艺以及施工条件的影响,导致其施工难度较大,存在较多的不安全因素。为了保障煤矿斜井施工的顺利进行,就需要对整个施工过程进行系统全面的分析研究,并采取有针对性的斜井施工技术,确保各项施工措施的顺利实施以及确保斜井的施工质量符合要求。
In the construction process of the mine,the inclined well is a very important part.Due to the address situation,construction technology and construction conditions,the construction is difficult and there are many unsafe factors.In order to ensure the smooth progress of the inclined shaft construction of the coal mine,it is necessary to carry out systematic and comprehensive analysis and research on the whole construction process,and adopt targeted inclined shaft construction technology to ensure the smooth implementation of various construction measures to ensure the construction of the inclined shaft and quality meets the requirements.
出处
《建筑技术开发》
2019年第12期39-40,共2页
Building Technology Development
关键词
煤矿
斜井
掘进
coal mine
inclined well
tunneling