摘要
因地震带下复杂地质螺旋隧道工程状况复杂,对技术要求更加严格,控制隧道施工引起的地层变形和保障隧道的施工安全尤为重要。通过理论研究与现场施工,研究施工工序与技术要点,并得出结论,可为类似工程提供借鉴。
Due to the complex conditions of complex geological spiral tunnels under earthquakes, the technical requirements are more stringent. It is especially important to control the formation deformation caused by tunnel construction and ensure the safety of tunnel construction. Through theoretical research and on-site construction, the construction process and technical points are studied, and come to the conclusion, hope to provide reference for similar projects.
作者
刘明才
王秋林
李仕民
房博
王清标
Liu Ming-cai;Wang Qiu-lin;Li Shi-min;Fang Bo;Wang Qing-biao
出处
《建筑技术开发》
2019年第12期115-117,共3页
Building Technology Development
关键词
螺旋隧道
全断面
深孔预注浆
spiral tunnel
whole section
deep hole pre-grouting