以保山硅基产业园标准厂房及配套基础设施(一期)建设项目为工程背景,分析工程特点并通过方案对比分析,确定选用现场加工、地面制作的技术方案。详细介绍施工工艺流程及技术保证措施,从施工质量、经济效益、施工进度方面分析施工效果。结果表明,该技术方案的实施,效果显著,实现预期的各项目标。
Based on Baoshan Silicon-based Industrial Park standard factory building and supporting infrastructure (Phase I) construction project,the engineering characteristics are analyzed and the technical scheme of field processing and ground fabrication is determined by comparison and analysis of the schemes. The construction process and technical guarantee measures are introduced in detail. The construction effect is analyzed from the aspects of construction quality,economic benefit and construction progress. The results show that the implementation of the technical scheme achieves remarkable results and achieved the expected objectives.
作者
余绍彪
拜继梅
刘奇
杨学用
杨曾龙
YU Shaobiao;BAI Jimei;LIU Qi;YANG Xueyong;YANG Zenglong(YCIH No.4 Construction Co.,Ltd.,Kunming,Yunnan 650000,China)
出处
《施工技术》
CAS
2019年第14期126-129,共4页
Construction Technology
关键词
厂房
屋面
彩钢瓦
铺装
施工技术
workshop
roofs
color steel tile
pavement
construction