嘉陵江利泽航运枢纽船闸总体布置研究 被引量:1

Research on the General Layout of Lize Navigation Junction Shiplock of Jialing River
下载PDF
导出
摘要 利泽航运枢纽采用左船闸右厂房的整体布置方案。依托工程自身特点,结合水工模型试验,对各级流量下船闸上下游引航道通航水流条件进行了分析研究,提出了解决引航道口门区附近纵横流速以及回流速度过大的改善措施,进一步实现了对船闸总体布置的优化。 Lize Navigation Junction adopts the general layout scheme of lock locates left and powerhouse locates right. Based on the characteristics of the project itself and combined with hydraulic model test, the navigation flow conditions of the upstream and downstrea1m approach channel of the shiplock with different flow rates are analyzed and studied, and the improvement measures to solve the excessive longitudinal and transverse flow velocity and return flow velocity near the approach channel entrance area are proposed, which further realizes the optimization of the general layout of the shiplock.
作者 刘大川 LIU Dachuan(Chongqing Navigation Construction Development (Group) Co., LTD, Chongqing, 401121)
出处 《四川水力发电》 2019年第4期137-140,共4页 Sichuan Hydropower
关键词 利泽航运枢纽 船闸 引航道 通航水流 总体布置 试验 研究 Lize Navigation Junction shiplock approach channel navigation flow general layout test research
  • 相关文献

参考文献1

二级参考文献1

  • 1尹崇清;刘亚辉.嘉陵江苍溪航电枢纽工程整体水工模型试验研究报告[R]重庆:重庆交通大学,西南水运工程科学研究所,201034-41.

共引文献3

同被引文献1

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部