双代号时标网络图在构建工业机器人工作站中的应用

Application of Dual Code Time Scale Network Diagram in Construction of Industrial Robot Workstation
下载PDF
导出
摘要 传统软件设计的项目工期管控方法,如“计划评审技术”“甘特图”等,不能直观的表示某项任务的紧急程度以及是否会影响到软件开发周期,且没有专用的软件进行任务规划.通过建筑领域应用广泛的ccproject软件,将“横道图”与“双代号时标网络图”分别应用于工业机器人工作站构建的工期管控中,并通过“双代号网络图”找到影响工期的关键线路,将工作站的开发周期由19天缩短至了17天.可以得出,“双代号网络图”是切实可行的软件项目任务规划方法. Project duration control methods of traditional software design, such as "plan review technology*1,"gantt chart”,which can't visually indicate whether the urgency of a task affects the software development cycle. And there is no dedicated software for task planning. In this paper, through the ccproject software widely used in the construction field, the "crossroad map" and "double-code time-scale network map” are respectively applied to the construction period control of industrial robot workstation construction. The key lines affecting the construction period were found through the Mdual-code network diagram", and the development cycle of the workstation was shortened from 19 days to 17 days. It can be concluded that "double code network diagram11 is a feasible method of software project task planning.
作者 刘良斌 彭雯 张志田 赵自鹏 LIU Liang-bin;PENG Wen;ZHANG Zhi-tian;ZHAO Zi-peng(Hunan Industry Polytechnic, Changsha Hunan 410208)
出处 《长沙航空职业技术学院学报》 2019年第3期79-81,85,共4页 Journal of Changsha Aeronautical Vocational and Technical College
基金 2018年湖南省哲学社会科学基金项目“新工科背景下高职学生工程素养与‘双创’能力培养研究”(编号:18YBG010)阶段性研究成果
关键词 双代号时标网络图 工期管控 工业机器人工作站 dual code time scale network chart time limit management and control robot workstation