平面分段流水线多目标模糊调度方法及仿真 被引量:4

Multi-Objective Fuzzy Scheduling Method for Panel Block Assembly Line and Its Simulation
下载PDF
导出
摘要 针对平面分段加工时间和交货期的不确定性,采用模糊数表示这两种时间参数;并以减少工时消耗和满足JIT生产要求为调度目标,建立了平面分段流水线多目标模糊调度问题的数学模型。提出了求解该问题的一种多目标文化基因算法,实现了分段的分配和排序两个子问题的同时优化。通过数值计算和仿真,对比了基于确切加工时间制定的常规调度方案和基于模糊加工时间制定的模糊调度方案。结果表明,模糊调度方案的执行力更强,证实了模糊调度方法的有效性。 Considering the uncertainties of the processing time and the due date of each panel block, the two temporal parameters are represented with fuzzy numbers. The multi-objective fuzzy scheduling problem of panel block assembly line was formulated in order to reduce working hours and to meet JIT requirements. A multi-objective memetic algorithm was proposed to solve this problem, simultaneously optimizing two sub-problems of assigning and sequencing panel blocks. Numerical calculations and simulation experiments were conducted to compare the scheduling schemes based on exact processing time or fuzzy processing time. The results show that fuzzy scheduling schemes have stronger executive powers, which demonstrates the effectiveness of the fuzzy scheduling method.
作者 杨志 柳存根 兰宏凯 YANG Zhi;LIU Cun-gen;LAN Hong-kai(State Key Laboratory of Ocean Engineering, Shanghai Jiao Tong University, Shanghai 200240, China;Collaborative Innovation Center for Advanced Ship and Deep-Sea Exploration, Shanghai 200240, China)
出处 《计算机仿真》 北大核心 2019年第8期439-444,共6页 Computer Simulation
基金 国家重点基础研究发展计划(2013CB036103) 海洋工程国家重点实验室基金项目(GKZD10010)
关键词 平面分段 模糊调度 多目标优化 文化基因算法 Panel block Fuzzy scheduling Multi-objective optimization Memetic algorithm
  • 相关文献

参考文献3

二级参考文献50

  • 1左燕,谷寒雨,席裕庚.大规模流水线调度的瓶颈分解算法研究[J].控制与决策,2006,21(4):425-429. 被引量:10
  • 2KARIMI N, ZANDIEH M, KAR-AMOOZ R. Bi-objective group scheduling in hybrid flexible flowshop: a multi-phase ap- proach[J]. Expert Systems with Applications, 2009, 37 (6) : 4024-4032.
  • 3YAGMAHAN B, YENISEY M M. Ant colony optimization for multi-objective flowshop scheduling problem[J]. Comput- ers b-Industrial Engineering, 2008, 54(3) :411-420.
  • 4GAJPAL Y,RAJENDRAN C,ZIEGLER H. An ant colony al- gorithm for scheduling in flowshops with sequence-dependent setup times of jobs [J]. International Journal of Advanced Manufacturing Technology, 2006, 30(5/6) :416-424.
  • 5ALEXANDROS D C, CHRISSOLEON P T. Exact analysis of a two-workstation one-buffer flow line with parallel unreliable machines [J]. European Journal of Operational Research, 2009,197(2) : 572-580.
  • 6OMAR M K, TEO S C, YASOTHEI S. Mixed integer pro- gramming formulation for hybrid flow shop scheduling problem [C]//Proceedings of the 2010 IEEE Conference on IEEM. Washington,D. C. ,USA:IEEE,2010:385-389.
  • 7CHEN C L, CHEN C L. A bottleneck-based heuristic for minimizing makespan in a flexible flow line with unrelated par- allel machines [J]. Computers & Operations Research, 2009, 36(11) ~3073-3081.
  • 8TAVAKKOLI-MOGHADDAM R, SAFAEI N R,SASSANI F. A memetic algorithm for the flexible flow line scheduling problem with processor blocking[J]. Computers & Opera- tions Research, 2009, 36(2).. 402-414.
  • 9LEE K J, LEE J K, CHOI S Y. A spatial scheduling system and its application to ship building: DAS-CURVE [J]. Expert Systems with Applications, 1996, 10(3/4):311-324.
  • 10MIN S G, LEE M W, MOON C U, et al. A genetic algo- rithm application for the load balancing of ship erection process[J]. IE Interfaces, 2000,13(2) : 225-233.

共引文献6

同被引文献14

引证文献4

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部