大藤峡水利枢纽右岸滑坡体综合治理方案研究

Study on comprehensive treatment plan of landslide mass on right bank of Datengxia hydro junction
下载PDF
导出
摘要 文中论述了大藤峡水利枢纽工程右岸滑坡体的成因及复杂的地质条件,针对滑坡体上部全强风化岩体、中部塌滑堆积物、底部弱风化及下部基岩内存在多层顺坡向软弱夹层的地质状况,通过稳定分析计算,进行多方案技术经济比选,提出较为合理的设计方案,为相似地质条件的边坡治理设计提供参考。 The paper discusses the cause of the landslide mass on right bank of the Datengxia hydro junction and the complex geological conditions.According to the geological situations including the complete highly weathered rock mass at the upper part of the landslide mass,the collapse deposit in the middle part,the moderately weathered rock at the bottom part,and the base rock with along slope multilayer weak intercalated layer at the lower part,through the stability analysis calculation,the paper carries out technical and economic comparison among multi schemes and puts out the reasonable design scheme,which could provide reference for side slope treatment design with similar geological conditions.
作者 郑军 张逍 刘晓明 张继军 ZHENG Jun;ZHANG Xiao;LIU Xiao -ming;ZHANG Ji -jun
出处 《东北水利水电》 2019年第9期4-5,30,71,共4页 Water Resources & Hydropower of Northeast China
关键词 水利枢纽 滑坡体 多层顺坡向软弱夹层 边坡治理 大藤峡 hydro junction landslide mass along aspect multilayer weak intercalated layer side slope treatment Datengxia
  • 相关文献

参考文献2

二级参考文献22

共引文献18

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部