660MW煤电机组调试期间调试电源容量选择

Capacity Selection of Power Supply Capacity During Commissioning of 660MW Coal-Fired Power Unit
下载PDF
导出
摘要 实测统计了某660MW煤电机组调试期间点火吹管、汽机冲3000r、整套启动电气短路试验3个阶段的用电量,得出了该电厂调试期间最大用电量出现的阶段、最大用电量以及影响用电量的因素,可为其他工程选择调试电源容量提供借鉴。 The electricity consumption during commissioning of a 660 MW coal power unit in three stages of ignition and blowing pipe steam engine charging 3000 r and complete set of electrical short circuit test was measured and counted.The maximum power consumption stage,maximum power consumption and the factors affecting the power consumption during commissioning of the power plant are obtained.which can provide reference for other projects to choose the commissioning power capacity.
作者 付启兵 方威 FU Qi-bing;FANG Wei(CPI Power Engineering Company Ltd.,Shanghai 200233,China)
出处 《工程建设与设计》 2019年第17期142-145,共4页 Construction & Design for Engineering
关键词 调试 负荷 利用系数 吹管方式 调试电源容量 commissioning power load utilization coefficient blowing mode commissioning capacity of power supply
  • 相关文献

参考文献1

二级参考文献5

共引文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部