连续近距离、多段大高差深基坑群与基础桩群统筹优化施工技术 被引量:2

GENERAL CONSTRUCTION OPTIMIZATION FOR CONTINUOUS AND NEAR DISTANCE DEEP FOUNDATION PIT GROUP AND FOUNDATION PILE GROUP WITH LARGE HEIGHT DIFFERENCE
下载PDF
导出
摘要 北京大兴国际机场中南指廊施工中,针对不规则排布的大高差基础桩群与大高差狭长基坑群的复杂位置关系,统筹优化施工顺序、灌注桩作业面选择和降水井插入时机,使基础工程施工流程有条不紊,减少了施工干扰,加快了施工进度. The complex position relation among irregularly arranged foundation pile group and narrow and long foundation pit group with large height difference was considered during middlesouth airside concourse construction of Beijing Daxing International Airport, to generally optimize the construction sequence, selection of filling pile construction area, and insertion of dewatering well, realizing smooth foundation construction, reducing construction interference and shortening the construction schedule.
作者 邵九婷 常乃麟 张治华 SHAO Jiu-ting;CHANG Nai-lin;ZHANG Zhi-hua(Beijing Mechanism Construction C o.,Ltd.,100045,Beijing,China)
出处 《建筑技术》 2019年第9期1100-1104,共5页 Architecture Technology
关键词 深基坑群 基础桩群 统筹优化 deep foundation pit group foundation pile group general optimization
  • 相关文献

参考文献5

二级参考文献20

共引文献57

同被引文献19

引证文献2

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部