摘要
对盘锦地震台GC-8600型气相色谱仪安装与调试情况进行了介绍,对安装、调试过程中存在的问题做了详细的阐述,并提出相应的解决办法,以满足观测要求,投入正式观测。通过对GC-8600型气相色谱仪安装与调试,初步实现盘锦地震台气体观测从模拟到半自动化转型。
This article introduced the installation and debugging of GC-8600 gas chromatograph in Panjin Seismic Station,expounded the problems existing in the process of installation and debugging,and put forward some corresponding solutions to meet the requirements of observation and put into formal observation.Through installation and debugging of GC-8600 gas chromatograph,the transformation of gas observation in Panjin Seismic Station from simulation to semi-automation is preliminarily realized.
作者
郭红霞
韩艳
杨昆
刘子哲
GUO Hong-xia;HAN Yan;YANG Kun;LIU Zi-zhe(Panjin Seismic Station,Liaoning Panjin 124010,China)
出处
《防灾减灾学报》
2019年第3期46-50,共5页
Journal of Disaster Prevention And Reduction
关键词
气相色谱仪
安装
调试
观测
gas chromatograph
installation
debugging
observation