白鹤滩混凝土坝浇筑效率提升措施 被引量:2

Efficiency improvement measures of the whole concrete pouring process in Baihetan Hydropower Station
下载PDF
导出
摘要 白鹤滩水电站大坝为300 m级特高拱坝,大坝混凝土工程量大、施工强度高、施工环境复杂.为保证大坝浇筑强度满足进度和质量要求,通过对混凝土生产、水平运输、垂直运输、平仓振捣各环节进行分解,采用定位技术和重量传感等进行缆机运行效率采集和分析,制定一系列技术和管理措施,有效提升了大坝浇筑“一条龙”效率. Baihetan Hydropower Station is a 300m-class extra-high arch dam with large amount of concrete engineering,high construction intensity and complex construction environment.In order to ensure the strength of dam concrete construction meet the requirements of schedule and quality,the project managers decompose all aspects of concrete production,horizontal transportation,vertical transportation,and concrete pouring,apply the positioning technology and weight sensing technology to collect and analyze the efficiency of the cable crane operation.Then,a series of technical and management measures were formulated to effectively improve the efficiency of the whole process of dam pouring.
作者 高世奎 周孟夏 杨支跃 谭尧升 刘春风 裴磊 Gao Shikui;Zhou Mengxia;Yang Zhiyue;Tan Yaosheng;Liu Chunfeng;Pei Lei
出处 《中国水利》 2019年第18期45-47,共3页 China Water Resources
关键词 大坝浇筑 “一条龙” 效率提升 缆机 concrete construction of dam "the whole process" efficiency improvement cable crane
  • 相关文献

参考文献3

二级参考文献2

共引文献10

同被引文献61

引证文献2

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部