依据主管部门发布的装配式混凝土结构质量管控办法,结合工程项目实践,从前期深化设计、部品部件生产、部品部件安装施工等阶段,阐述具体质量管控措施和达到的效果,确保装配式混凝土结构的施工质量可控。
According to the quality control method of monolithic precast concrete shear wall structure issued by the competent department,and combined with the engineering project practice,the concrete quality control measures and effects are elaborated from the stages of deepening design,production of parts and installation and construction of parts,so as to ensure that the construction quality of monolithic precast concrete shear wall structure can be controlled.
作者
沈嵘
张明明
SHEN Rong;ZHANG Mingming(Nanjing Construction Installation Project Quality Supervision Station,Nanjing Jiangsu 210000,China;Nanjing Dadi Construction Group Co.,Ltd.,Nanjing Jiangsu 210042,China)
出处
《工程质量》
2019年第9期25-29,共5页
Construction Quality
关键词
装配整体式剪力墙结构
集中约束搭接连接
质量管控
monolithic precast concrete shear wall structure
rebar bundle lapping in grout-filled holeconfined with spiral hoop
quality control