为满足北京市S5线提速要求,须将京通线41号怀沙河大桥6孔24 m T梁予以更换。受现场条件限制,传统的吊装更换、预铺横移更换T梁方案难以实施,因而探讨了使用架桥机在营业线上换梁施工的技术方案。通过选用DJK160型架桥机和严密的施工组织与控制,实现了在营业线上每6 h更换1孔梁。本文介绍了换梁方案、架桥机的关键参数、施工流程和关键环节的控制措施,供类似工程参考。
In order to meet the speed raising requirement of Beijing S5 suburban railway,it is neccessary to replace 6 spans 24 m T-girder of No. 41 bridge on Beijing-Tongliao railway. Constrained by the site constructon conditions, traditional method by hoisting replacement and pre-laying and transverse movement is difficult to carry out. So the grider replacement method using girder-erecting machine on orperation railway was discussed and applied. By using DJK160 type girder-erecting manchine and strict construction organization and control,the time replacing one girder was limted in 6 h,that is a maintenance window. In this paper,the girder replacement scheme,key parameters of girder-erecting manchine,construction technology process and control measurements of key process were introduced. It may provide references for similar engineering.
作者
孙秀峰
SUN Xiufeng(Construction Department,China Railway Beijing Bureau Group Corporation,Beijing 100860,China)
出处
《铁道建筑》
北大核心
2019年第9期44-47,共4页
Railway Engineering
关键词
铁路桥梁
营业线
架桥机
T梁
换梁施工
railway bridge
operation railway
girder-erecting manchine
T-girder
girder replacement