昆明岩溶地区桩基设计和施工问题探讨 被引量:7

IDEALS ABOUT DESIGN AND CONSTRUCTION OF PILE FOUNDATION IN KUNMING KARST AREA
下载PDF
导出
摘要 受多个断裂构造及其活动的影响,昆明地区喀斯特岩溶地基的水文地质情况极为复杂,导致区域内此类场地上高层建筑桩基设计和施工具有很大的难度.结合工程案例和实践经验,探讨类似地基上的工程地质勘察和与桩基设计施工相关的地下水影响及其控制、桩端嵌岩深度、孔底沉渣厚度控制等问题,并提出具体方法措施. Controlled by many fracture structures and their activities, the hydro-geological conditions of karst foundation in Kunming are very complex, which leads to many difficulties in the design and construction of the pile foundation of high rise buildings in such an area. According to the engineering cases and practical experience, engineering geological prospecting, problems about groundwater impact assessment, rock socket-ed depth, control of the thickness of sediment and etc. were discussed, and some specific methods, measures and key points were put forward.
作者 秦云 张军 解志勇 王文渊 张鹏 QIN Yun;ZHANG Jun;XIE Zhi-yong;WANG Wen-yuan;ZHANG Peng(Yunnan University,650091,Kunming,China;China Construction Second Engineering Bureau Ltd.,100010,Beijing,China)
出处 《建筑技术》 2019年第10期1166-1169,共4页 Architecture Technology
关键词 岩溶地基 地下水 桩端嵌岩深度 沉渣厚度控制 karst foundation groundwater rock socket-ed depth control of the thickness ofsediment
  • 相关文献

参考文献1

二级参考文献17

  • 1陈剑平,石丙飞,王清.工程岩体随机结构面优势方向的表示法初探[J].岩石力学与工程学报,2005,24(2):241-245. 被引量:41
  • 2杜时贵,王思敬.岩石质量指标(RQD)的各向异性分析[J].工程地质学报,1996,4(4):48-54. 被引量:18
  • 3Deere D U. Technical Description of Rock Cores for Engineering Purposes [J]. Rock Mechanics and Engineering Geology, 1963,1 ( 1 ) : 18 - 22.
  • 4Zhang W, Wang Q, Chen J P, et al. Determination of the Optimal Threshold and Length Measurements for RQD Calculations[J]. International Journal of Rock Mechanics and Mining Sciences, 2012, 52:1 -12.
  • 5Zhang W, Chen J P, Cao RQD and Generalized Z X, et al. Size Effect of Representative Volume Elements.. A Case Study on an Underground Excavation in Baihetan Dam, Southwest China [J]. Tunneling and Underground Space Technology, 2013, 35 : 89 - 98.
  • 6Hudson J A, Priest S D. Discontinuity Frequency in Rock Mass [J ]. International Journal of Rock Mechanics and Mining Sciences and Geomechanics Abstracts, 1983,20(2):75 - 89.
  • 7Priest S D, Hudson J A. Discontinuity Spacing in Rock [J]. International Journal of Rock Mechanics and Mining Sciences and Geomechanics Abstracts, 1976,13 (5) :135 - 148.
  • 8Senz Z, Kazi A. Discontinuity Spacing and RQD Estimates from Finite Length Scanlines [ J ]. International Journal of Rock Mechanics and Mining Sciences and Geomechanics Abstracts, 1984,21 (4): 203 - 212.
  • 9Priest S D. Discontinuity Analysis for Rock Engineering[M]. London: Chapman & Hall, 1993.
  • 10Zhang W, Chen J P, Liu C, et al. Determination of Geometrical and Structural Representative Volume Elements at the Baihetan Dam Site [J]. Rock Mechanics and Rock Engineering, 2012, 45: 409- 419.

共引文献8

同被引文献39

引证文献7

二级引证文献23

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部