摘要
本文以四台矿8702综采工作面为工程背景,针对5702回风巷进行锚杆、锚索受力监测和巷道变形监测。通过监测巷道围岩表面位移、锚杆索受力分析等来评价支护效果。结果表明:该高强度、高预紧力锚杆+短锚索强力支护技术在大幅提高巷道掘进速度的同时,能够有效控制巷道围岩变形,取得较好效果。
Based on the engineering background of 8702 fully mechanized mining face in Sitai Mine, the stress monitoring of bolt and cable and the deformation monitoring of roadway in 5702 air return roadway are carried out. The supporting effect is evaluated by monitoring the surface displacement of surrounding rock and stress analysis of bolt cable. The results show that the high strength, high pre-tension bolt + short anchor cable strong support technology can effectively control the deformation of surrounding rock while greatly improving the roadway driving speed, and achieve better results.
作者
刘明
Liu Ming(Sitai Coal Mine, Datong Coal Mine Group Co., Ltd., Shanxi Datong 037052)
出处
《山东煤炭科技》
2019年第10期36-38,41,44,共5页
Shandong Coal Science and Technology
关键词
锚杆
支护
监测
分析
bolt
support
monitoring
analysis