瓦托水电站厂房尾水肘管二期混凝土预埋拔管施工技术研究 被引量:2

Study on Construction Technology of Pre-embedded Pipe Drawing of Second Stage Concrete for Tailrace Elbow Tube of Watuo Hydropower Station
下载PDF
导出
摘要 水电站渐变型钢衬肘管二期混凝土浇筑完毕其钢衬底部极易形成脱空区。发电后,在高速水流冲击下将引起钢衬的震动、加大气蚀而缩减钢衬的使用寿命。阐述了钢衬混凝土浇筑时采用的预埋拔管接触灌浆施工技术,避免了肘管底部产生空腔,确保了工程质量。 After the second stage concrete casting of elbow tube with gradual steel lining in hydropower station, the steel lining substrate is easy to form a void area. After power generation, the vibration of steel lining will be caused under the impact of high-speed water flow, the cavitation erosion will be increased, and the service life of steel lining will be reduced. This paper expounds the construction technology of contact grouting by pre-embedded drawn pipe for steel lining concrete casting, which avoids the cavity at the bottom of elbow tube and ensures the quality of the project.
作者 刘福友 赵亚 张建祥 LIU Fuyou;ZHAO Ya;ZHANG Jianxiang(First Branch of Sinohydro Bureau 7 Co., LTD, Pengshan, Sichuan, 620860)
出处 《四川水力发电》 2019年第5期30-31,46,共3页 Sichuan Hydropower
关键词 肘管 预埋 拔管 接触灌浆 瓦托水电站 elbow tube pre-embed pipe drawing contact grouting Watuo Hydropower Station
  • 相关文献

参考文献1

二级参考文献5

共引文献2

同被引文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部