朱昌河水库大坝碾压混凝土浇筑温控关键技术 被引量:2

Key Technology of Temperature Control for RCC Pouring of Zhuchanghe Reservoir Dam
下载PDF
导出
摘要 贵州盘县朱昌河水库工程区域属亚热带夏湿春干温暖气候,冬无严寒夏无酷暑,适宜坝体碾压混凝土全年浇筑。然而,该区域夏季阳光直射升温明显,暴晒环境下气温能达到35℃左右;冬季温度相对适宜,但可能遇到极短时间的凝冻天气。在该区域如需保证碾压混凝土全年浇筑,也需要制定合理的温控措施。通过有效控制机口混凝土温度、控制初凝时间、分块分仓及层厚控制、混凝土运输遮盖、斜层快速铺筑工艺、仓面喷雾保湿降温和浇筑后分期通水冷却及覆盖喷淋洒水养护管理等关键温控措施,合理有效地保障了高低温时段大坝碾压混凝土的浇筑质量。 Zhuchanghe Reservoir Project in Panxian County, Guizhou Province, has a subtropical dry and warm climate in summer, wet and dry in spring, with no severe cold in winter and no severe heat in summer. It is suitable for the construction of RCC pouring of dam body throughout the year. However, direct sunshine warms up obviously in summer, and the temperature can reach about 35℃ in the exposure environment. The temperature in winter is relatively suitable, but it may encounter freezing weather for a very short period of time. Therefore, reasonable temperature control measures need to be formulated if RCC is to be poured throughout the year in this area. By effectively controlling the concrete temperature of the machine mouth, controlling the initial setting time, dividing the blocks and storages and controlling the thickness of the concrete, transporting the concrete, covering the slope, rapidly laying the inclined layer, storing the surface, spraying the moisture and cooling down, pouring the cooling water after the stages and covering the sprinkling and sprinkling and maintaining the water, the quality of the roller compacted concrete is guaranteed reasonably and effectively.
作者 杨普锋 刘猛 YANG Pu-feng;LIU Meng(Second Branch of China Water Resources and Hydropower Sixth Engineering Bureau Co.,Ltd.,Dandong,Liaoning Province,118001)
出处 《云南水力发电》 2019年第5期111-115,共5页 Yunnan Water Power
关键词 碾压混凝土 混凝土温度 初凝时间 斜层快速铺筑 通水冷却 喷雾保湿 覆盖 roller compacted concrete concrete temperature initial setting time inclined layer rapid paving water cooling spray moisturizing coverage
  • 相关文献

参考文献6

二级参考文献14

  • 1《混凝土重力坝设计规范》(SL319-2005).
  • 2丁宝瑛.混凝土坝温度控制设计的优化[J].水力学报,1982,(1).
  • 3潘家铮.水工建筑物的温度控制[M].水利电力出版社,1990.
  • 4《水工混凝土砂石骨料试验规程》(DL/T5151-2001).
  • 5《碾压混凝土坝设计规范》(SL 314- 2004).
  • 6《混凝土重力坝设计规范》(DL 5108- 1999).
  • 7《水工碾压混凝土施工规范》(DL/T5112- 2009).
  • 8《水工混凝土掺用粉煤灰技术规范》(DL/T5055- 2007).
  • 9李丽.碾压混凝土筑坝技术在世界的发展[J].中国水利,2000(10):23-24. 被引量:5
  • 10张镜剑.碾压混凝土坝的历史、现状和趋势[J].华北水利水电学院学报,2000,21(3):1-7. 被引量:11

共引文献12

同被引文献9

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部