摘要
文中论述了万家寨引黄工程南干一级泵站高边坡原设计施工的情况、度汛中发现的问题,重新采取的加固处理措施和处理结果的效果分析并由此引发了作者关于施工监理工作的一些思考。
In this paper,the Writers deseribed first the status in design and construction (stone masonry,was completed in Sept,2000)of the high slope(64.8m in Vertical height)in Pumping station NO.1, of the south main line,Wanjiazhai YRDP,secondly described the problems which had occurred in the high slope during flood season in 2001,thirdly described the strenghening measures taken anew in the position where the problems had once occurred in the high slop mentioned above and described the analysis on the effect of the high slope′s design and construction.These matters have led the writers to think about the supervising work,which was or is being implemented in the construction like in Wanjiszhai YRDP.
出处
《山西水利科技》
2002年第4期62-64,共3页
Shanxi Hydrotechnics