摘要
介绍了二烧 75m2 烧结机实施厚料层烧结所采取的措施 ,以及改造后取得的效果。
In order to increase the quality and quantity of sinter,the modification of increasing the bed depth of №3 sintering plant in Ma Aashan I&S Co was conducted in the year 2001 and the expecting effect was obtained
出处
《烧结球团》
北大核心
2002年第6期37-39,共3页
Sintering and Pelletizing
关键词
烧结机
厚料层烧结
技术改造
deep bed sintering,modification of sintering plant,measurement