西安南京铁路东秦岭特长隧道设计方案的研究 被引量:3

A Study on Design Program of East Qinling Super-long Tunnel of Xi'an-Nanjing Railway
下载PDF
导出
摘要 西安南京铁路东秦岭特长隧道全长 12 2 6 8m ,设计为双线加平行导坑方案 ,钻爆法施工。隧道进出口各 35m采用模筑混凝土衬砌 ,洞身其余地段采用复合式衬砌 ,支护均以喷、锚、网为主 ,并辅以钢架。隧道设计总工期为 5 8.32个月 ,是全线的控制性工程。从地质特征、方案比选。 East Qinling Super-long Tunnel has a total length of 12,268m. According to design, the twin-track tunnel with parallel heading shall be excavated using drill and blast method. Form concrete lining shall be applied to the sections 35m to entrance and exit, and composite lining shall be applied to the remaining part. Shotcreting, anchor bolts and wire mesh are principal supporting means assisted with steel frame. The tunnel is the control project of Xi'an-Nanjing Railway, and is scheduled to be completed in 58.32 months. Design program of the tunnel is illustrated from geological characteristics, selection of program, and structural design, etc.
出处 《铁道标准设计》 2002年第11期6-9,共4页 Railway Standard Design
关键词 东秦岭特长隧道 设计方案 铁路隧道 双线隧道 地质特征 正洞 平行导坑 结构设计 railway tunnel , twin-track tunnel , geological characteristics , program , main tunnel , parallel heading , structural design
  • 相关文献

同被引文献4

引证文献3

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部