介绍了黄州坝隧道进口无轨运输和出口有轨运输的施工方案。通过对两方案工序衔接、循环时间和部分工序成本进行比较 ,指出有轨运输在长大隧道施工中技术先进 ,经济合理 。
In this paper the construction plans of rail transport and trackless transport in Huangzhouba tunnel are introduced. And the tow plans are compared on process continuity, cycle time and cost. At last author points out that the rail transport is more advanced, economical and reasonable than trackless transport in long tunnel construction and represent the construction trend of long tunnel.
出处
《山西建筑》
2002年第11期31-32,共2页
Shanxi Architecture